|
Standing on the
Shoulders of a Giant To See the Future of Formal Planning by Carol Ptak and Chad Smith The Giant Joe
Orlicky was truly a giant. When he wrote the first book on
Material
Requirements Planning (MRP) in 1975 only 700 companies had implemented
the
concept. “As this book goes into print, there are some 700 manufacturing companies or plants that have implemented, or are committed to implementing, MRP systems. Material requirements planning has become a new way of life in production and inventory management, displacing older methods in general and statistical inventory control in particular. I, for one, have no doubt whatever that it will be the way of life in the future.”
MRP
did become the way of life in manufacturing. The
codification and subsequent commercialization of MRP
fundamentally
changed the industrial world. Orlicky recognized the opportunity
presented
by changing manufacturing circumstances and the invention of the
computer that
enabled a planning approach never before possible. “Traditional inventory
management approaches, in pre-computer days, could obviously not go
beyond the
limits imposed by the information processing tools available at the
time. Because of this almost all of those
approaches and techniques suffered from imperfection.
They simply represented the best that could
be done under the circumstances. They acted as a crutch and incorporated
summary, shortcut and
approximation methods, often based on tenuous or quite
unrealistic assumptions, sometimes force-fitting concepts to
reality so as to
permit the use of a technique. The breakthrough, in
this area, lies in the simple fact that once a computer becomes
available, the
use of such methods and systems is no longer obligatory.
It becomes feasible to sort out, revise, or
discard previously used techniques and to institute new ones that
heretofore it
would have been impractical or impossible to implement.
It is now a matter of record that among
manufacturing companies that pioneered inventory management computer
applications in the 1960s, the most
significant results were achieved not by those who chose to improve,
refine,
and speed up existing procedures, but by those who undertook a
fundamental
overhaul of their systems.” In
the first edition of Orlicky’s MRP, Orlicky made the case for a
fundamental
reexamination of how companies planned and managed inventory and
resources. This case was so compelling
that the concepts that he brought to the table proliferated throughout
the
industrial world within two decades. Industry
now faces another time of transition and re-examination.
The circumstances under which Orlicky and his
cadre developed the rules behind MRP and Distribution Requirements
Planning
(DRP) have dramatically changed. Customer
Tolerance Times are much shorter. Product
variety has risen dramatically. Supply
Chains have extended around the world.
Product complexity has risen. Outsourcing
is more prevalent. Product life cycles
have reduced. Reductions in working
capital are mandated. In
a nutshell, there are more complex planning and supply scenarios than
ever
before in history. The complexity comes
from multiple directions; ownership, the market, engineering and sales
and the
supply base. While this complexity has
risen, the potential of technology has progressed and
accelerated.
The lack of significant financial return on
technology investments would strongly suggest that this potential has
been
squandered. Software is a tool that
translates and reinforces rules into a routine.
If the rules behind the software are inappropriate and outdated then we
must change the rules before we change the tools. In recent
years, however, industry and
software providers have attempted to combat increasing complexity with
better
software applications; applications with the old rules embedded at
their core. The net effect is that we have improved the
efficiency of doing the wrong or inappropriate things. Money and
energy spent to optimize antiquated
rules with increasingly sophisticated tools is wasteful, distractive
and
counterproductive. Given the current world of increased variability and
volatility; conventional MRP and DRP logic now requires a fundamental
overhaul. We think Orlicky would agree.
Seeing the Future Our
self imposed mission was to stand on the shoulders of Joe Orlicky’s
incredible
vision in order to see further. This
white paper and the latest edition of Orlicky’s MRP proposes elegant
and
intuitive MRP and DRP rule sets to address the volatile 21st
Century
landscape. Complexity cannot be combated with more
complexity. Effective
rules and subsequent tools are necessary for the demand driven world to
enable
companies’ resources and assets to move closer to actual demand.
There
can be no more lip service to small incremental changes that may or may
not
improve the company’s performance; concrete and proven tactics are
required
that drive sustainable bottom line results. Furthermore, the
tension
between the formal planning and the Lean communities must be
eliminated; they
need each other desperately. To
better understand the context of the required change, the following
five
questions need to be asked:
Successful businesses follow a very
simple formula. A clear vision must lead
to the appropriate rules which then lead to the appropriate
tools.
Simply put companies get into trouble when
this sequential progression is broken. MRP
enables organizations to quickly calculate and synchronize total
requirements given
the rate of demand. This is of
particular importance when the company has a deep bill of material or
many
shared components. Is this vision still
valid? Absolutely! Due to the increased variability and
volatility in manufacturing today the vision of MRP is more relevant
today than
ever.
At
the heart of every supply chain is manufacturing. At the heart of
manufacturing is MRP. Supply chains are not the simple linear
structures normally represented as a straight line from the supplier’s
supplier
to the customer’s customer. Supply
chains are three dimensional web-like entities that are difficult to
graphically represent. Each node in the
web is a different MRP system.
Question 2: What Rules Need to
Change with MRP?
If
the vision of MRP is still relevant, why is MRP failing and perceived
as
outdated? MRP has many well known
shortcomings. The result of MRP’s
shortcomings is that companies have chronic and frequent shortages at
various
stages of the production, procurement and fulfillment cycles.
These chronic and frequent shortages tend to
lead to three main effects. Companies
frequently can identify many of these problems at the same time.
Experienced
planning personnel are not blind to the shortcomings of MRP.
These have been discussed for years around
the world at APICS meetings. However,
these shortcomings have been further exacerbated by the variability and
volatility in today’s hypercompetitive environment. Materials and
Production Control personnel
often find themselves in a dilemma regarding their MRP system.
There are powerful aspects of MRP that are
still relevant and necessary. For
example, given the need to be able to plan complex product structures
across a
complex supply chain well in advance of customer demand means that some
aspects
of MRP are even more relevant today than 40 years ago. Companies
desperately need visibility within
today’s more complex planning scenarios. So, what are some of the rules that need to Change? Below is a short list of some of the bigger issues. A more complete list of shortcomings and their corresponding effects to organizations can be found on a table below.
Question 3: Why do Lean and other pull-based techniques often come into conflict with MRP? In
addition to the rise of volatility and complexity referred to earlier,
the
proliferation of Lean and other pull-based philosophies has put
additional
pressure on planning personnel and MRP systems. The
fundamentally different view of inventory puts Lean
advocates and
planning personnel at odds. Many Lean
implementations attempt to abandon MRP completely.
This causes tremendous friction between them
and the planning personnel responsible for ensuring a reliable source
of
supply. Question 4: MRP progress in the last 30 years? Software
providers, consultants and the academic community have had ample
opportunity to
fix MRP’s shortcomings. Why has MRP not
progressed?
In the new edition of Orlicky’s Material
Requirements
Planning, MRP for the 21st Century; Demand Driven MRP (DDMRP)
is
introduced. Demand Driven MRP represents
a fusion of the still relevant vision of MRP but applies new rules and
corresponding
tools in order to marry that vision with competing in the demand driven
world. DDMRP moves formal planning logic
from the world of “Push and Promote” to “Position and Pull.”
At its
core, DDMRP uses a new type of strategically positioned and dynamically
managed
stock position to dampen variability, compress lead times and reduce
working
capital requirements while ensuring unprecedented levels of service. The positions dramatically alter the planning
and execution rules of conventional MRP. In
most manufacturing environments, inventory stock in some form is a
requirement. As mentioned previously, a
primary reason to hold inventory is that customer tolerance times are
shrinking. Customers will no longer
tolerate long lead times. However, most
manufacturing companies and certainly every supply chain cannot be a
pure make
to order system. Would you wait at the
grocery store for a quart of milk if you knew the cow had not even been
milked? What about at the gas station if
the oil had not yet been drilled? Holding
inventory is a reality in the modern world. In
most cases, companies cannot position and
manage stock positions effectively because they have only antiquated
stock
practices and tools. There are many who believe that carrying inventory is a waste. Inventory is waste only if it is located in the wrong places and in the wrong quantities. The key is to determine first where the right places are to stock and only then determine the amounts to be stocked. Next the process must allow those places and amounts to change as the environment and conditions change. The effective management of inventory is a dynamic closed loop process. This is necessary to effectively leverage the working capital and capacity commitment inherent in inventory to maximize the company’s overall financial performance.
At
the same time it is also extremely wasteful to not carry inventory. When companies lean out too much inventory,
then frequent shortages can result. When
companies experience shortages they are forced to spend additional
time, effort,
money and capital in order to resolve the problem and significant
market
opportunities can be missed. The Critical Positioning Factors
These
above six factors must be applied systematically across the entire bill
of
material, routing structure, manufacturing facilities and supply chain
to
determine the best positions for purchased, manufactured and finished
items
(including service parts). The bigger
the system these factors are applied to, the more significant the
results can
be.
Chad Smith is currently a partner with the Demand Driven Institute as well as cofounder and managing partner of Constraints Management Group, a services and technology company specializing in pull-based manufacturing, materials, and project management systems for mid-range and large manufacturers. He has been at the forefront of developing and articulating Demand Driven MRP (DDMRP) and is also an internationally recognized expert on the Theory of Constraints (TOC). Copyright � Demand Driven Institute.
Reproduced with permission. |
Copyright � 2018 PSQ |